THE FROST WALLS GO UPPART I: PUTTING UP THE FORMS |
|
![]() |
|
Several days after the footers were poured, Fern Dumoulin and Gene Knox were busy taking down the footer forms. |
|
| Friday, September 5, 2008, began early for the Polar Bears Club volunteers. All hands were ready to assist Marty Morgan's crew when they arrived at 7:00 a.m. Many thanks to Marty for his generous donation of time, labor, materials and expertise in helping the Club reach this point in construction! | |
![]() |
|
Frank Duguay, from Morgan Concrete, and Bob Stickney discussed the plan for setting up the forms. |
|
| The first job of the day was to get the 124, 3' x 8' forms into the footer trenches. | |
![]() |
|
John Blais and Ron Russell began the
task ... |
|
![]() |
|
... along with Gene Knox and Louise, |
|
![]() |
|
Bob, and Sam Stickney. |
|
![]() |
![]() |
Frank Duguay and his assistants (both of whom were named Dan!) began setting up the forms at the northwest corner of the building. |
|
![]() |
|
Frank Duguay fastens rebar along the north wall. (That's Gene Knox with his back to the camera!) |
|
|
![]() |
It wasn't long before Ron, John, and Gene had learned the ropes of assembling the forms and tying in the rebar |
|
![]() |
|
With the north, east, and west wall forms up, Ron and Bob began putting up the catwalks along the outer perimeter of the forms. |
|
![]() |
![]() |
While Frank tied in the last row of rebar, John and Dan put in the final panel at the southeast corner. |
|
![]() |
|
By 10:00 the forms were up. Morgan's crew still had some work to do around the doors, but the concrete was ordered and expected around 2 o'clock that afternoon. We're ready for the pour! |
|