DOORS, SIDING, ETC.Continued from previous page. |
||
| 11/23/08 - Paneling begins on the south side of the garage. | ||
![]() |
||
| Bob and Sam Stickney put up the metal
siding. |
||
![]() |
||
Bob and Sam Stickney and Gene Knox trim
the siding to fit. |
||
| 12/2/08 - 12/3/08 - The weather cooperates and the siding goes up quickly. | ||
![]() |
![]() |
|
Sam, Bob, and Gene .... that's Ivan
Arsenault securing the ladder. |
||
| 12/5/08
The overhead light gets installed and
the staging comes down. |
||
|
![]() |
|
![]() |
||
![]() |
||
After the staging is down, Sam and Bob prepare a stop for the garage doors to come down on. This is necessary because the doors will be installed to come down to where the concrete floor will be. |
||
| 12/9/08 - It may be snowing, but the work continues! | ||
![]() |
||
Sam and Bob complete the installation of the overhead light on the north side of the building. using a generator to check that the light does work. |
||
|
||
Meanwhile, inside, Reggie, from Reggie's
Door Service, begins
installing the 14 foot wide overhead doors. |
||
12/18/08
- A few more things to finish up before the garage is buttoned up. |
||
![]() |
![]() |
|
Sam and Bob pre-drill the corner siding pieces before ... |
...installing. |
|
![]() |
![]() |
|
Sam completes the door-stop for the
overhead door. |
||
|
||
![]() |
||
Although there is still much more work to be done, the groomer garage is now ready for occupation by the Tucker and drag! |
||